Gearing up for commissioning and the test period.

Jul 9, 2020 | Progress update

Construction of the HaloSep process is in its final stages. All major pieces of equipment are in place, and the focus is on connecting everything through tubing and pipes, as well as installing the electrical wiring and controls. During the summer period, we will test components without adding any actual waste fluids or fly ash, in a so called cold test. Once all construction and cold test are completed, we will start running the HaloSep process at Vestforbraending in a series of controlled steps that include adding actual scrubber liquid and fly ash. We are all excited about seeing the HaloSep process live in a full-scale demonstration environment.